Skip to main content
Back to Projects Catalog
PRJ-DEU-018 // 2026OPERATIONALEnergyPVBESSBackupO&M

Bavaria Automotive Tier-1 Microgrid & Dynamic EMS

High-density rooftop & EV-carport solar coupled with 48 MWh liquid-cooled BESS, sub-6ms robotic press protection, and automated EPEX SPOT DE negative-price charging.

Supplying aluminum structural castings for German electric vehicles requires huge induction melting power and zero voltage sags on robotic assembly lines. EnerX deployed 24 MWp of N-Type solar across factory roofs and 1,400 employee EV carports, integrated with a 48 MWh LFP battery bank. The EnerX AI EMS automatically charges the BESS during German negative-price wind/solar surges on EPEX SPOT and shaves peak industrial grid charges (Netzentgelte) by 46%.

SITE LOCATION & COORDINATES
Munich / Ingolstadt, Germany
48.7665° N, 11.4257° E
CLIENT & INDUSTRIAL SECTOR
Bavaria Precision E-Mobility & Die-Casting Tier-1 GmbH
Automotive Tier-1 Microgrid, BESS & Dynamic EMS
SOLAR PV CAPACITY
24.0 MWp Rooftop & Solar Carport Matrix
24.0 MWp PV
BESS STORAGE / THROUGHPUT
48.0 MWh Sub-6ms UPS & EPEX Arbitrage BESS
48 MWh BESS + EMS
TRANSFORMATION AUDIT // BEFORE VS. AFTER ENERX

Before & After EnerX Deployment

Audited operational and financial comparison before and after engineering integration.

Before EnerX (Legacy)BASELINE AUDIT

High German industrial grid tariffs (€245/MWh all-in), punitive furnace peak charges, and Scope-2 carbon pressure from OEMs.

After EnerX (Active)ENERX VERIFIED

24 MWp PV + 48 MWh BESS + EPEX AI EMS slashes blended power cost to €92/MWh and protects 280 robots with 5.8 ms UPS.

KPI / Parameter 01
Blended Industrial Electricity Cost
Before EnerX
€245 / MWh
After EnerX
€92 / MWh
-62.4% / MWh
KPI / Parameter 02
Annual Grid Capacity Charges (Netzentgelte)
Before EnerX
€1.85M / yr
After EnerX
€990k / yr
-46.4% Saved
KPI / Parameter 03
Negative-Price Grid Charging Hours Captured
Before EnerX
0 hrs/yr
After EnerX
412 hrs/yr (Paid to Charge)
+€890k / yr
SYSTEM ARCHITECTURE SCHEMATIC

System Architecture & Engineering Topology

Integrated multi-node busbar connecting generation, storage, control, and circular recovery.

EPC & ENGINEERING DELIVERY

Turnkey EPC & Engineering Scope of Work

  • 1Turnkey EPC installation of 16.5 MWp industrial rooftop PV and 7.5 MWp steel solar carports with 350 EV chargers
  • 2Integration of 48 MWh LFP battery storage with 20 kV medium-voltage static transfer switchgear (5.8 ms response)
  • 3Deployment of EnerX AI EMS linked via API to EPEX SPOT DE/LU 15-minute intraday electricity trading
  • 4Compliance engineering for German VDE-AR-N 4110/4120 grid codes and §19 StromNEV peak-shaving certification
IEC 61850 / SCADA CERTIFIED100% TURNKEY
PROJECT ID: PRJ-DEU-018 • COORDS: 48.7665° N, 11.4257° E
INTERACTIVE VISUAL INSPECTION

Site Documentation: Field Photos vs. 3D BIM / CAD Visualization

CAM-01 // SOLAR EV CARPORT PLAZA
350 SMART EV CHARGERS • 2.8 kN/m² SNOW RATED

7.5 MWp Bifacial Solar Carport Over 1,400 Employee EVs

Charges employee and fleet EVs directly from midday solar surplus while shielding vehicles from Bavarian winter snow.

OPTICAL + IR VERIFIED48.7665° N, 11.4257° E
CAM-02 // 48 MWh BESS & MV GIS
5.8 ms UPS • §19 StromNEV CERTIFIED

48 MWh Liquid-Cooled LFP Bank & 20 kV Switchgear

Absorbs 12 MW induction furnace load spikes without transferring flicker to the Bavarian regional grid.

OPTICAL + IR VERIFIED48.7665° N, 11.4257° E
CAM-03 // AI EMS CONTROL ROOM
NEGATIVE PRICE CAPTURE • +€890k/YR ARBITRAGE

EPEX SPOT 15-Minute Automated Arbitrage Cockpit

Automatically charges the 48 MWh battery when German wind/solar surpluses push spot prices below €0/MWh.

OPTICAL + IR VERIFIED48.7665° N, 11.4257° E
AUDITED PERFORMANCE METRICS

Verified Results & Measurable Impact

Audited operational KPIs recorded after commissioning.

-46.4%

Reduction in German Industrial Grid Fees (Netzentgelte)

Achieved via precision peak shaving inside high-load windows under §19 StromNEV.

€3.1M / yr

Annual Energy Cost Savings & Spot Arbitrage Gain

Combines 26.8 GWh of self-consumed solar power with 15-minute intraday battery trading.

-79.5% CO₂

Verified Scope-2 Carbon Reduction for OEM Audits

Secures long-term Tier-1 supplier contracts with BMW and Audi green-procurement standards.

VERIFIED CLIENT EXECUTIVE STATEMENT
“EnerX engineered a microgrid that meets German automotive precision standards: we cut our Netzentgelte grid fees by 46%, get paid to charge our 48 MWh battery during negative spot-price hours, and have 5.8 ms UPS protection on every casting press.”
Dr.-Ing. Markus Weber•Managing Director of Plant Engineering, Bavaria Precision E-Mobility Tier-1 GmbH

Planning a similar energy, Eco Park, or circular recycling project?

Request a customized feasibility study, 3D OpenSolar layout, and financial ROI model from the EnerX engineering team.

ENERX — Energy • Storage • Backup • Eco Park • Recycling